Nostroy 2.15. Internal engineering networks of buildings and structures. Recommendations for the installation of internal pipeline systems for water supply, sewerage and fire safety, including the use of polymer pipes. Starting heating systems

Introduction
1 area of ​​use
2 Normative references
3 Terms and definitions, designations and abbreviations
4 General provisions
5 Pressure pipe products
5.1 Requirements for pressure pipe products
5.2 Pressure pipes
5.2.1 Pressure steel pipes
5.2.1.1 Connecting parts for steel pipes
5.2.1.2 Connections for steel pipes
5.2.2 Pressure copper pipes
5.2.2.1 Connecting parts for copper pipes
5.2.2.2 Connections for copper pipes
5.2.3 Pressure metal-polymer pipes
5.2.3.1 Connecting parts for metal polymer pipes
5.2.3.2 Connections for metal-polymer pipes
5.2.4 Pressure pipes made of polypropylene
5.2.4.1 Connections for polypropylene pipes
5.2.4.2 Connections for polypropylene pipes
5.2.5 XLPE pressure pipes
5.2.5.1 Connecting parts for cross-linked polyethylene pipes
5.2.5.2 Connections for XLPE pipes
5.2.6 Chlorinated polyvinyl chloride pressure pipes
5.2.6.1 Connections for chlorinated polyvinyl chloride pipes
5.2.6.2 Connections for chlorinated polyvinyl chloride pipes
5.2.7 Polybutene pressure pipes
5.2.7.1 Connections for polybutene pipes
5.2.7.2 Connections for polybutene pipes
5.2.8 Acrylonitrile butadiene styrene pressure pipes
5.2.8.1 Connecting parts for acrylonitrile butadiene styrene pipes
5.2.8.2 Connections for acrylonitrile butadiene styrene pipes
5.3 Technological features connections of pressure polymer pipes
5.3.1 Types of connections for pressure polymer pipes
5.3.2 Welding of polyolefin pressure pipe products
5.3.3 Connections of pressure pipe products made of unplasticized polyvinyl chloride, chlorinated polyvinyl chloride and acrylonitrile butadiene styrene
5.3.4 Welding pressure pipe products made of polypropylene
5.4 Fastening of pressure pipelines
6 Sewer pipe products
6.1 Requirements for sewer pipe products
6.2 Sewer pipes
6.2.1 Gray cast iron sewer pipes
6.2.1.1 Connecting parts for sewer pipes gray cast iron
6.2.1.2 Connections for sewer pipes made of gray cast iron
6.2.2 Ductile iron sewer pipes
6.2.2.1 Connecting parts for sewerage pipes made of ductile cast iron
6.2.2.2 Connections for ductile iron sewer pipes
6.2.3 Unplasticized polyvinyl chloride sewer pipes
6.2.3.1 Connecting parts for sewer pipes made of unplasticized polyvinyl chloride
6.2.3.2 Connections for sewer pipes made of unplasticized polyvinyl chloride
6.2.4 Thick-walled sewer pipes made of polyvinyl chloride
6.2.4.1 Connecting parts for thick-walled PVC sewer pipes
6.2.4.2 Connections for thick-walled PVC sewer pipes
6.2.5 Polyethylene sewer pipes
6.2.5.1 Connecting parts for sewer pipes made of polyethylene
6.2.5.2 Connections for polyethylene sewer pipes
6.2.6 Filled polyethylene sewer pipes
6.2.6.1 Connecting parts for sewer pipes made of filled polyethylene
6.2.6.2 Connections for sewer pipes made of filled polyethylene
6.2.7 Polypropylene sewer pipes
6.2.7.1 Connecting parts for sewer pipes made of polypropylene
6.2.7.2 Connections for socketed sewer pipes made of polypropylene
6.2.8 Filled polypropylene sewer pipes
6.2.8.1 Connecting parts for sewer pipes made of filled polypropylene
6.2.8.2 Connections for sewer pipes made of filled polypropylene
6.2.9 Connections for assembling different sewer pipes
6.3 Fasteners for gravity pipelines
7 Pipe procurement work
7.1 Bending pipes for pressure and sewer pipelines
7.2 Production of pipe blanks from pressure pipes for water pipelines
7.3 Manufacturing of pressure hoses polyethylene pipes for water pipes
7.4 Production of pipe blanks for internal fire water supply systems
7.5 Manufacturing of water seals for internal drains
7.6 Manufacturing of units from polymer sewer pipes
7.7 Equipping package shafts with pressure water supply and sewer pipe blanks
7.8 Equipping plumbing cabins with pressure water supply and sewer pipe blanks
7.9 Manufacturing riser bays for internal drains
8 Installation internal water pipes
8.1 Typical structures technological processes installation of internal water pipes
8.2 Technical documentation for installation and assembly work
8.3 Organization of work on installation of internal water supply systems
8.4 Preparatory work
8.5 Auxiliary works
8.6 Assembly of internal water pipes
9 Installation of sewer pipelines
9.1 Typical structures of installation processes internal sewerage
9.2 Requirements for the internal sewerage design
9.3 Requirements for installation project internal sewerage
9.4 Assembling the internal sewer system
9.5 Quality control of sewer pipeline assembly
10 Installation of internal drains
10.1 Installation of internal drainage systems
10.2 Typical structures of technological processes for installing internal drains
10.3 Production installation work for the assembly of internal drains
10.4 Quality control of internal drains assembly
11 Internal tests pipeline systems
11.1 Testing cold and hot water pipes
11.2 Testing of fire water pipes
11.3 Testing of sewer pipelines
11.4 Testing internal drains
12 Handover and acceptance of internal pipelines
12.1 General provisions
12.2 Handover and acceptance of internal water pipelines
12.3 Delivery and acceptance of internal sewerage
12.4 Handover and acceptance of internal drains
13 Safety precautions, Fire safety and environmental safety when installing internal pipeline systems
Appendix A (for reference). Legend sewer pipe products
Appendix B (recommended). Inspection report form hidden work By internal systems water supply and sanitation
Appendix B (recommended). Form of report based on test results of cold/hot water supply
Appendix D (recommended). Form of report based on test results of the internal sewerage system
Appendix E (recommended). Form of report based on the test results of the internal drainage system
Appendix E (recommended). Sample certificate of testing the internal fire-fighting water supply system for operability
Appendix G (recommended). Sample test report for internal fire water supply for water loss
Appendix I (recommended). Sample test report for fire hydrants for serviceability
Appendix K (recommended). Sample acceptance certificate for internal fire-fighting, utility and hot water pipelines
Appendix L (recommended). Sample certificate of acceptance of internal sewerage
Appendix M (recommended). Sample acceptance certificate for internal drains
Bibliography

Introduction. 2

1 area of ​​use. 2

3. Terms and definitions, designations and abbreviations. 4

4. General provisions. 5

5. Technology of work execution. 8

5.1. Technology for manufacturing components and parts of pipelines from steel pipes. 8

5.2. Complete set and preparation for installation of sanitary equipment, heating devices, components and parts of pipelines. 10

5.3. Installation and assembly work. General provisions. eleven

5.4. Internal cold and hot water supply. 12

5.5. Heating and heat supply. 12

6. Testing of internal sanitary systems... 14

6.1. General provisions for testing cold and hot water supply, heating and heat supply systems. 14

6.2. Internal cold and hot water supply systems. 15

6.3. Heating and heat supply systems. 15

7. Start-up of heating systems. 16

Appendix A. Dimensions of holes and grooves for laying pipelines (air ducts) in ceilings, walls and partitions of buildings and structures. 18

Appendix B. Form of inspection report for hidden work. 19

Appendix B. Form of hydrostatic or manometric leak test report. 20

Appendix D. Form of individual equipment testing report. 21

Appendix E. Form of acceptance certificate for internal cold and hot water supply systems. 22

Appendix E. Form of acceptance certificate for internal heating systems. 23

Bibliography. 24

Introduction

This standard was developed within the framework of the Standardization Program of the National Association of Builders and is aimed at implementing the “Urban Planning Code Russian Federation", Federal Law of December 27, 2002 No. 184-FZ "On Technical Regulation", Federal Law of December 30, 2009 No. 384-FZ "Technical Regulations on the Safety of Buildings and Structures", Federal Law No. 261-FZ "On energy saving and on increasing energy efficiency and on introducing amendments to certain legislative acts of the Russian Federation”, order of the Ministry of Regional Development of the Russian Federation dated December 30, 2009 No. 624 “On approval of the List of types of work on engineering surveys, on preparation project documentation, construction, reconstruction, major renovation capital construction projects that affect the safety of capital construction projects.”


STANDARD OF THE NATIONAL ASSOCIATION OF BUILDERS

1.1. This standard establishes the rules for the performance of work, installation, testing and commissioning of heating, hot and cold water supply systems.

2. Normative references

GOST 12.1.044-89 System of occupational safety standards. Fire and explosion hazard of substances and materials. Nomenclature of indicators and methods for their determination

GOST 12.3.003-86 System of occupational safety standards. Electric welding works. Safety requirements


GOST 8946-75 Connecting parts made of malleable cast iron with cylindrical threads for pipelines. The angles are passable. Main Dimensions

GOST 9416-83 Construction levels. Specifications

GOST 15180-86. Flat elastic gaskets. Main parameters and dimensions

GOST 16037-80 Welded joints steel pipelines. Main types, structural elements and dimensions

GOST 17375-2001 Seamless welded pipeline parts made of carbon and low-alloy steel. Steeply curved bends, type 3D (R about 1.5DN). Design


GOST 19185-73 Hydraulic engineering. Basic concepts. Terms and Definitions

GOST 19431-84 Energy and electrification. Terms and Definitions

GOST 24054-80 Mechanical engineering and instrument making products. Leak testing methods. General requirements

GOST 25136-82 Pipeline connections. Leak test methods

GOST 25151-82 Water supply. Terms and Definitions

GOST 30494-96 Residential and public buildings. Indoor microclimate parameters

GOST R 50618-93 Single-layer metal compensatory bellows. Types, general technical requirements

GOST R 50619-93 Compensatory multilayer metal bellows. Types, general technical requirements

GOST R 52948-2008 Fittings made of copper and copper alloys for connecting copper pipes by pressing. Specifications

GOST R 53484-2009 Shredded flax. Specifications

SNiP 2.04.01-85 Internal water supply and sewerage of buildings

SNiP 3.01.04-87 Acceptance into operation of completed construction facilities. Basic provisions

SNiP 3.05.01-85 Updated edition Internal sanitary systems

SNiP 12-01-2004 (SP 48.13330.2011) Organization of construction. Updated edition

SNiP 12-03-2001 Labor safety in construction. Part 1. General requirements

SNiP 12-04-2002 Labor safety in construction. Part 2. Construction production

SNiP 41-01-2003 Heating, ventilation and air conditioning

Note- When using this standard, check the validity of reference standards and classifiers in the public information system - on the official websites of the national body of the Russian Federation for standardization and NOSTROY on the Internet or according to annually published information indexes published as of January 1 of the current year. If reference document replaced (changed), then when using this standard you should be guided by the new (changed) document. If the reference document is canceled without replacement, then the provision in which a reference to it is given applies to the part that does not affect this reference.

3. Terms and definitions, designations and abbreviations

3.1. This standard uses terms in accordance with GOST 19185, GOST 25151, as well as the following terms with corresponding definitions:

3.1.1 water heating: Type of space heating using liquid coolant.

Note- Water or water-based antifreeze can be used as a coolant.

3.1.2 internal sanitary systems: Heating systems, hot and cold water supply of the building.

3.1.3. performer of work (contractor): A legal entity or individual performing construction and installation work under an agreement with the customer.

3.1.4. fault: Disturbances in the operation of heat supply and (or) water supply systems, in which at least one of the requirements determined by the technological process is not met.

3.1.5. finished floor mark: Marking the floor surface taking into account the finishing of the floor covering.

3.1.6 heating: Artificial heating of premises in order to compensate for heat losses in them and maintain a temperature at a given level, determined by the conditions of thermal comfort for people in the room.

3.1.7 panel heating: A type of heating in which heat is transferred to the heated room from heated flat surfaces of heating panels located in walls and partitions.

3.1.8 steam heating: A type of heating in which the coolant is steam supplied to the heating system from the heating network.

3.1.9 press connection: Connection of pipelines by cold mechanical deformation of the metal between the press fitting and the pipe covered by it to the depth of the socket.

3.1.10 press fitting: A system element stamped in a special way for press connections of heating and water supply units.

Note- An element of the system can be a bend, a transition, a tee, etc.

3.1.11 test pressure: Excessive pressure at which a hydraulic test of a pipeline or its individual components must be carried out for strength and tightness.

3.1.12 operating pressure: The greatest excess pressure that occurs during system operation, without taking into account the hydrostatic pressure of the medium.

3.1.13 operating parameters of the transported medium: The maximum temperature and highest possible water pressure in the supply pipeline, taking into account the operation of pumping stations.

3.1.14 network water: Water continuously circulating in heating networks.

3.1.15 engineering networks: Pipelines for various purposes laid in the territories settlements, as well as in buildings.

Note- In this standard, pipelines are understood as water supply, sewerage, heating, etc.

3.1.16 water supply system: Building engineering systems that consume heat for heating, ventilation and hot water supply.

3.1.17 heat supply system (HS): A set of interconnected power plants that supply heat to a region, city, or enterprise.

[GOST 19431-84, paragraph 26]

3.1.18 heat consumption system: A complex of heat-consuming power plants with connecting pipelines providing heating and hot water supply in buildings and structures.

3.1.19 heating point: A set of devices designed to connect heating, ventilation, air conditioning, and hot water supply systems to residential and public buildings to heat networks.

Note- Heating points can be individual (ITP) or central (CTP). Individual heating points are intended for connecting heat consumption systems of one building or part thereof, and central ones - for two or more buildings.

3.1.20 coolant: Working fluid in heating systems.

3.1.21 Maintenance building: A set of works to maintain the good condition of the building, its specified parameters and operating modes structural elements and technical devices.

3.1.22 conditional excess pressure Р У, MPa: Pressure corresponding to operating conditions at normal operating temperature.

3.1.23. operating organization: A legal or natural person who, on the rights of the owner or on behalf of the owner (investor), operates the constructed building.

3.2. The following designations and abbreviations are used in the standard:

D nap - outside diameter pipeline, mm;

P pr - excess pressure, MPa;

FUM tape thread sealing tape made of fluoroplastic sealing material.

4. General provisions

4.1. Installation of internal sanitary systems must be carried out in compliance with the requirements of SNiP 12-01-2004, SNiP 12-03-2001, SNiP 12-04-2002, instructions from equipment manufacturers, as well as this standard.

4.2. Manufacturing and installation of units and parts of heating systems and pipelines to ventilation units with water temperatures above 388 K (115 °C) and steam with a working pressure of more than 0.07 MPa (0.7 kgf/cm2) should be performed in accordance with PB 10-573-03.

4.3. Installation of sanitary systems should be carried out when buildings are ready for construction in the following volumes:

For industrial buildings(up to 5000 m3) - in the volume of the entire building;

For industrial buildings (over 5000 m3) - in the volume of a part of the building, including a separate production room, workshop, span, etc. or a set of devices (including internal drains, heating unit, ventilation system, etc.);

For residential and public buildings up to five floors - in the volume of a separate building, one or several sections of the building;

For residential and public buildings over five floors - in the amount of five floors of one or more sections of the building.

Note- A different installation organization scheme is possible depending on the adopted design scheme of sanitary systems.

4.4. Before installation of internal sanitary systems begins, the following work must be completed:

Installation of interfloor ceilings, walls and partitions on which sanitary equipment will be installed;

Construction of foundations or sites for the installation of water heaters, pumps, air heaters and other sanitary equipment;

Installation of waterproofing in places where units of water heaters and pumps are installed;

Laying inputs for external communications of sanitary systems into the building;

Installation of floors (or appropriate preparation) in places where heating devices are installed on stands;

Installation of supports for pipelines laid in underground channels and technical undergrounds;

Preparation of holes, grooves, niches and nests in foundations, walls, partitions, ceilings and coatings necessary for laying pipelines;

Note- The dimensions of holes and grooves for laying pipelines in ceilings, walls and partitions of buildings and structures are given in Appendix A, unless other dimensions are provided for by the project. The sealing of holes in ceilings, walls and partitions after laying pipelines should be done tightly, with a fire resistance material not lower than the fire resistance of the barrier being crossed.

Applying auxiliary marks on the internal and external walls of all premises;

Note- Places for applying auxiliary marks are determined by the design marks of the finished floor plus 500 mm.

Installation of window frames, and in residential and public buildings- installation of window sill boards;

Plastering (or cladding) the surfaces of walls and niches in places where sanitary and heating appliances are installed, pipelines are laid, as well as plastering the surface of grooves for hidden installation of pipelines in external walls;

Preparation of installation openings in walls and ceilings for supplying large-sized equipment;

Installation in accordance with the working documentation of embedded parts in building structures for fastening equipment and pipelines;

Ensuring the possibility of turning on power tools, as well as electric welding machines, at a distance of no more than 50 m from one another;

Glazing window openings in external fences, insulation of entrances and openings in external fences.

4.5. General construction, sanitary and other special work should be carried out in sanitary facilities in the following order:

Preparation for the installation of floors, plastering of walls and ceilings, installation of beacons for the installation of ladders;

Installation of fastening means, laying of pipelines and carrying out their hydrostatic or pressure testing (see GOST 25136 and GOST 24054); waterproofing of floors;

Priming walls, installing clean floors;

Installation of bathtubs, brackets for washbasins and mounting parts for flush cisterns;

First painting of walls and ceilings, tiling;

Installation of washbasins, toilets and flush cisterns;

Second painting of walls and ceilings;

Installation of water fittings;

Finishing work (including sealing holes in ceilings, walls and partitions after laying pipelines);

Installation of clean floors.

When installing sanitary systems and carrying out related civil works, there should be no damage to the floor, walls, ceiling, as well as structures and equipment installed in the building during previously performed work.

4.6. Welding of steel pipes should be done by any method in compliance with the requirements of GOST 12.3.003.

4.6.1. The types of welded joints of steel pipelines, the shape, and structural dimensions of the weld must comply with the requirements of GOST 16037.

4.6.2. Welding of galvanized steel pipes should be carried out with self-shielding wire (see GOST 2246) with a diameter of 0.8 to 1.2 mm or electrodes with a diameter of no more than 3 mm with a rutile or calcium fluoride coating, if the use of other welding materials is not provided for in the working documentation.

4.6.3. The connection of galvanized steel pipes, parts and assemblies by welding during installation should be carried out while ensuring local suction of toxic emissions or when cleaning the zinc coating to a length of 20 to 30 mm from the joining ends of the pipes, followed by coating the outer surface of the weld and the heat-affected zone with paint containing 94% zinc dust (by weight) and 6% synthetic binders (polysterol, chlorinated rubber, epoxy resin).

4.6.4. The connection of steel pipes, as well as their parts and assemblies with a nominal diameter of up to 25 mm inclusive, at a construction site should be made by lap welding (see GOST 16037) (with one end of the pipe spreading or a threadless coupling).

When welding, threaded surfaces and flange surfaces must be protected from splashes and drops of molten metal.

The weld should be free of cracks, cavities, pores, undercuts, unwelded craters, as well as burns and leaks of the deposited metal.

Holes in pipes with a diameter of up to 40 mm for welding pipes must be made by drilling, milling or cutting on a press.

The diameter of the hole must be equal to the internal diameter of the pipe with a permissible deviation of no more than 1 mm in the direction of increase.

4.7. When making a press connection, the ends of the pipes must be clean and free of scratches and grooves along the entire length or at least along the entire length of the insert. When delivering pipes with a synthetic coating made at the manufacturer, the surface of the pipes should not be damaged when this coating is removed.

4.8. Installation of sanitary systems in complex, unique and experimental buildings should be carried out in accordance with the requirements of Section 5 and design documentation.

4.9. When used in installation flexible hoses you should do the following:

Before installation, it is necessary to inspect the liner for the integrity of the fastening (crimping) of the end fittings, the presence of a gasket, damage to the threads, braiding and other defects that arose during storage and transportation;

Install flexible hoses with a bending radius that is at least 5 to 6 times greater than the outer diameter (or as indicated in the product data sheet);

Flexible lines should not be stretched or twisted during installation and after installation;

Do not apply excessive force when tightening the tip;

Note- When tightening the tip, there is a risk of damage to the seal. The tightening torque value is indicated in the product data sheet.

Flexible hoses should not be exposed to open flame or excessive heat;

Every six months it is necessary to inspect the flexible line and check the tightness of the end fittings;

Note- To carry out inspection, it is necessary to ensure free access to units with flexible connections.

Flexible hoses should be replaced every three years;

When installing end fittings (sleeve nuts), liners should not be used. sanitary linen and other seals capable of expanding in a humid environment, preventing excess thickness sealing tape when installing fittings, seal the nut only with a standard sealing gasket;

It is not allowed to install the liner in a tense state;

It is not allowed to operate the liner at sub-zero temperatures or near open flames;

When installing flexible hoses, preference is given to flexible bellows hoses (see GOST R 50618, GOST R 50619).

5. Work technology

Work on the installation of heating systems, hot and cold water supply should be carried out in accordance with GOST 30494, SNiP 3.05.01-85 Updated edition, SNiP 41-01-2003, SNiP 2.04.01-85.

5.1. Technology for manufacturing components and parts of pipelines from steel pipes

5.1.1. The manufacture of components and parts of pipelines from steel pipes should be carried out in accordance with GOST 8946, GOST 16037, GOST 25136. Manufacturing tolerances should not exceed the values ​​​​specified in table 1.

Table 1

5.1.2. The connection of steel pipes, as well as parts and assemblies made from them, should be performed by welding, threading, union nuts and flanges (to fittings and equipment), press connections (due to cold mechanical deformation of the metal between the press fitting and the pipe covered by it to the depth of the socket).

5.1.2.1. Galvanized pipes, assemblies and parts must be connected, as a rule, by threads using galvanized steel connecting parts or non-galvanized ductile iron (see GOST 8946), on union nuts and flanges (see GOST 12820, GOST 12821) or on a press fittings (see GOST R 52948).

5.1.2.2. For threaded connections of steel pipes, a cylindrical pipe thread according to GOST 6357 (accuracy class B) by rolling on light pipes and threading on ordinary and reinforced pipes.

When making threads using the rolling method on a pipe, it is allowed to reduce it internal diameter up to 10% along the entire length of the thread.

5.1.2.3. Turns of pipelines in heating and heat supply systems should be performed by bending pipes or using seamless welded bends made of carbon steel in accordance with GOST 17375.

Pipe bending radius:

With a nominal bore of up to 40 mm inclusive, there must be at least 2.5D pipe head;

With a nominal bore of 50 mm or more, there must be at least 3.5D pipe head.

5.1.3. In cold and hot water supply systems, turns of pipelines should be made by installing elbows in accordance with GOST 8946, bends or bending pipes. Galvanized pipes should only be bent when cold.

For pipes with a diameter of 100 mm or more, the use of bent and welded bends is allowed. The minimum radius of these bends must be at least one and a half nominal diameter of the pipe.

When bending welded pipes, the weld seam should be located on the outside pipe billet, and the seam plane must be at an angle of at least 45° to the bending plane.

5.1.4. Weld welding on curved sections of pipes in heating elements of heating panels is not allowed.

5.1.5. When assembling units, threaded connections must be sealed. As a sealant for threaded connections at liquid temperatures in pipes up to 378 K (105 °C) inclusive, FUM tape corresponding to TU 6-05-1388-86 or flax strands (see GOST R 53484) impregnated with red lead or white should be used , mixed with drying oil or special sealing pastes-sealants.

As a sealant for threaded connections at coolant temperatures in pipes above 378 K (105 °C) and for condensation lines, FUM tape corresponding to TU 6-05-1388-86 or asbestos strand together with flax strands should be used (see GOST R 53484 ), impregnated with graphite mixed with drying oil.

FUM tape (see TU 6-05-1388-86) and flax strands (see GOST R 53484) should be applied in an even layer along the thread, preventing protrusion in and out of the pipe.

As a sealant for flange connections at a coolant temperature of no more than 423 K (150 °C), gaskets 2 - 3 mm thick made of paronite, or fluoroplastic-4, according to GOST 15180 should be used, and at a temperature of no more than 403 K (130 °C) gaskets made of heat-resistant rubber according to GOST 7338.

5.1.6. The flanges are connected to the pipe by welding. Deviation from the perpendicularity of the flange welded to the pipe relative to the pipe axis is allowed up to 1% of the outer diameter of the flange, but not more than 2 mm.

The surface of the flanges must be smooth and free of burrs. The bolt heads should be located on one side of the connection.

On vertical sections of pipelines, the nuts must be placed at the bottom.

The ends of the bolts should not protrude from the nuts by more than 0.5 bolt diameters or 3 thread pitches.

The end of the pipe, including the flange-to-pipe welding seam, must not protrude beyond the flange surface.

Gaskets in flange connections must not overlap the bolt holes.

Installation of multiple or angled gaskets between flanges is not permitted.

5.1.7. Deviations linear dimensions of assembled units should not exceed ±3 mm for a length of up to 1 m and ±1 mm for each subsequent meter.

5.1.8. Assemblies of sanitary systems must be tested for leaks at the place of their manufacture.

Pipeline assemblies of heating systems, heat supply, internal cold and hot water supply, including those intended for embedding in heating panels, valves, taps, valves, mud pans, air collectors, elevators, etc., must be tested hydrostatic (hydraulic), manometric or bubble (pneumatic) method in accordance with GOST 25136 and GOST 24054.

5.1.9. When using the hydrostatic method of testing for leaks, air should be completely removed from the units, filled with water at a temperature of at least 278 K (5 °C) and kept under an excess pressure P pr equal to 1.5 P y.

If dew appears on the pipeline during testing, the test should be continued after it has dried or wiped off.

5.1.10. Assemblies made of steel pipes of sanitary systems are considered to have passed the test if there are no drops or spots of water on the surface and at the joints and there is no pressure drop during the test.

Valves, gate valves and faucets are considered to have passed the test if no drops of water appear on the surface and in the places of the sealing devices after turning the control devices twice (before testing).

5.1.11. With the bubble method of testing for leaks, pipeline components are filled with air with an excess pressure of 0.15 MPa (1.5 kgf/cm2), immersed in a bath of water and held for at least 30 seconds.

Assemblies that have passed the test are those which, when tested, do not produce air bubbles in the water bath.

Tapping connections, turning control devices and eliminating defects during testing are not allowed.

5.1.12. Outside surface assemblies and parts made of non-galvanized pipes, with the exception of threaded connections and the surface of the flange surface, must be coated with a primer, and the threaded surface of assemblies and parts must be coated with anti-corrosion lubricant taking into account the requirements of TU 36-808-85.

5.2. Complete set and preparation for installation of sanitary equipment, heating devices, components and parts of pipelines

5.2.1. Assemblies and parts made from pipes for sanitary systems must be transported to sites in containers or packages and have accompanying documentation.

Each container and package must have a label attached to it identifying the packaged units.

5.2.2. Fittings, automation devices, instrumentation, connecting parts, fastening devices, gaskets, bolts, nuts, washers, etc. not installed on parts and assemblies. must be packaged separately, and the labeling of the container must indicate the designations or names of these products.

5.2.3. Water heaters, air heaters, pumps, central and individual heating points, water metering units should be supplied to facilities under construction in transportable assembly-complete units with fastening means, piping, shut-off valves, gaskets, bolts, nuts and washers.

5.2.4. Sections cast iron radiators should be assembled into devices on nipples using sealing gaskets:

Made of heat-resistant rubber 1.5 mm thick at coolant temperatures up to 403 K (130 °C) according to GOST 7338;

Made of paronite with a thickness of 1 to 2 mm at a coolant temperature of up to 423 K (150 °C) according to GOST 15180.

5.2.5. Blocks of cast iron radiators and finned pipes must be tested in accordance with GOST 25136 using the hydrostatic method with a pressure of 0.9 MPa (9 kgf/cm2) or the bubble method with a pressure of 0.1 MPa (1 kgf/cm2). The results of bubble tests are the basis for submitting quality complaints to manufacturers of cast iron heating devices.

Blocks steel radiators must be tested using the bubble method according to GOST 25136 with a pressure of 0.1 MPa (1 kgf/cm2).

Convector blocks must be tested in accordance with GOST 25136 using the hydrostatic method with a pressure of 1.5 MPa (15 kgf/cm2) or the bubble method with a pressure of 0.15 MPa (1.5 kgf/cm2).

After the test, water must be removed from the heating units.

Heating panels after hydrostatic testing must be purged with air, and their connecting pipes must be closed with inventory plugs.

5.3. Installation and assembly work. General provisions

5.3.1. The connection of galvanized and non-galvanized steel pipes during installation should be carried out in accordance with 5.1.2.

Detachable connections on pipelines should be made at the fittings and where necessary according to the conditions of pipeline assembly. The removable detachable connection of the fittings must make it possible to replace the fittings.

Detachable connections of pipelines, as well as fittings for inspection and cleaning must be located in places accessible for maintenance.

5.3.2. Vertical pipelines should not deviate from the vertical by more than 2 mm per 1 m of length.

5.3.3. Uninsulated pipelines of heating systems, heat supply, internal cold and hot water supply should not be adjacent to the surface of building structures.

The distance from the surface of the plaster or cladding to the axis of uninsulated pipelines must be determined by the following conditions:

For nominal diameter up to 32 mm inclusive with open gasket the distance should be from 35 to 55 mm;

For diameters from 40 to 50 mm, the distance should be from 50 to 60 mm;

For diameters greater than 50 mm, the distance should be taken according to the working documentation.

The distance from pipelines, heating devices and heaters with a coolant temperature above 378 K (105 °C) to structures of buildings and structures made of flammable (combustible) materials in accordance with GOST 12.1.044 must be at least 100 mm.

5.3.4. Fastening means should not be located at pipeline junctions.

Sealing fasteners using wooden corks, as well as welding of pipelines to fastening means are not allowed.

The distance between the means of fastening steel pipelines in horizontal sections is determined according to Table 2, unless otherwise indicated in the design documentation.

When laying horizontal sections along traverses, the latter must be fixed on hangers on both sides of the traverse with nuts.

table 2

5.3.5. Means for fastening risers made of steel pipes in residential and public buildings are installed at a height equal to half the height of the building floor.

Means for fastening risers in industrial buildings should be installed at intervals of 3 m.

5.3.6. Connections to heating devices with a length of more than 1500 mm must have fastenings.

5.3.7. Sanitary and heating devices must be installed plumb (see GOST 7948) and level (see GOST 9416). Sanitary cabins must be installed on a level base.

5.3.8. Hydrostatic testing (see 5.1.9) or pressure testing in accordance with GOST 25136 of pipelines with hidden installation must be carried out before they are closed with the drawing up of an inspection report for hidden work in accordance with Appendix B and SNiP 12-01-2004.

Testing of insulated pipelines should be carried out before applying insulation.

5.3.9. Heating systems, heat supply, internal cold and hot water supply, boiler house pipelines upon completion of their installation must be washed with water until it comes out without mechanical suspensions.

5.4. Internal cold and hot water supply

5.4.1. The installation height of water fittings (distance from the horizontal axis of the fittings to sanitary fixtures) should be taken as follows:

Water taps and mixers from the sides of sinks - by 250 mm, from the sides of sinks - by 200 mm;

Toilet taps and mixers from the sides of washbasins - 200 mm.

5.4.2. The installation height of the taps from the finished floor level should be taken as follows:

800 mm for water taps in bathhouses, toilet flush taps, faucets for inventory sinks in public and medical institutions, faucets for bathtubs;

800 mm for vidouar mixers with oblique outlet;

1000 mm for direct outlet faucets;

1100 mm for mixers and oilcloth sinks in medical institutions, general mixers for bathtubs and washbasins, elbow mixers for surgical washbasins;

600 mm for taps intended for washing floors in toilet rooms of public buildings;

1200 mm for shower mixers.

5.4.3. Shower screens should be installed at the following height:

From 2100 to 2250 mm from the bottom of the mesh to the finished floor level;

From 1700 to 1850 mm from the bottom of the mesh to the level of the finished floor in cabins for the disabled;

1500 mm from the bottom of the pallet in preschool institutions.

Deviations from the specified dimensions should not exceed 20 mm.

Note- For sinks with backs that have holes for taps, as well as for sinks and washbasins with table-top fittings, the installation height of the taps is determined by the design of the device.

5.4.4. In showers for people with disabilities and in preschool institutions, shower nets with a flexible hose should be used.

In rooms for disabled people, cold and hot water, and mixers must be lever or push action.

Mixers for washbasins, sinks, as well as taps for flush tanks installed in rooms intended for disabled people with upper limb defects must have foot or elbow control.

5.5. Heating and heat supply

5.5.1. The slopes of the lines to the heating devices should be made from 5 to 10 mm per length of the line in the direction of movement of the coolant. For line lengths up to 500 mm, the pipes should not be sloped.

5.5.2. Connections to smooth steel, cast iron and bimetallic finned pipes should be made using flanges (plugs) with eccentrically located holes to ensure free removal of air and drainage of water or condensate from the pipes. For steam connections, concentric connection is allowed.

5.5.3. Radiators of all types should be installed at distances not less than:

60 mm from the floor;

50 mm from the bottom surface of the window sill boards;

25 mm from the surface of the plaster walls.

Note- Distances may vary if specified by the radiator manufacturer.

In the premises of medical, preventive and children's institutions, radiators should be installed at a distance of at least 100 mm from the floor and 60 mm from the wall surface.

If there is no window sill board, a distance of 50 mm should be taken from the top of the device to the bottom of the window opening.

When laying pipelines openly, the distance from the surface of the niche to the heating devices should ensure the possibility of laying connections to the heating devices in a straight line.

5.5.4. Convectors must be installed at a distance:

At least 20 mm from the surface of the walls to the fins of the convector without casing;

Close or with a gap of no more than 3 mm from the wall surface to the fins heating element wall convector with casing;

At least 20 mm from the wall surface to the casing of the floor convector.

The distance from the top of the convector to the bottom of the window sill must be at least 70% of the depth of the convector.

The distance from the floor to the bottom of a wall-mounted convector with or without a casing must be at least 70% and no more than 150% of the depth of the installed heating device.

If the width of the protruding part of the window sill from the wall is more than 150 mm, the distance from its bottom to the top of convectors with a casing must be no less than the lifting height of the casing necessary to remove it.

Connecting convectors to heating pipelines should be done by threading or welding.

5.5.5. Smooth and ribbed pipes should be installed at a distance of at least 200 mm from the floor and window sill board to the axis of the nearest pipe and 25 mm from the plaster surface of the walls. The distance between the axes of adjacent pipes must be at least 200 mm.

5.5.6. When installing a heating device under a window, its edge on the riser side, as a rule, should not extend beyond the window opening. At the same time, the combination vertical axes symmetry of heating devices and window openings is not necessary.

5.5.7. IN single pipe system heating with one-sided open connection of heating devices, the riser to be laid should be located at a distance of 150 ± 50 mm from the edge of the window opening, the length of the connections to the heating devices should be no more than 400 mm.

5.5.8. Heating devices should be installed on brackets or on stands manufactured in accordance with the working documentation or supplied complete with heating devices.

The number of brackets should be set based on:

One bracket per 1 m2 of heating surface of a cast iron radiator, but not less than three brackets per radiator (except for radiators in two sections);

Two brackets per pipe (for finned pipes).

Instead of upper brackets, it is allowed to install radiator strips, which should be located at 2/3 of the height of the radiator.

The brackets should be installed under the radiator necks; for finned pipes, the brackets should be installed under the pipes at the flanges.

When installing radiators on stands, the number of stands should be:

Two for up to 10 sections;

Three when the number of sections is more than 10, and the top of the radiator must be secured.

5.5.9. The number of fasteners per convector block without casing should be:

Two fastenings to the wall or to the floor for single-row and double-row installation;

Three wall mounts or two floor mounts for 3-row and 4-row installations.

For convectors supplied complete with mounting means, the number of fastenings is determined by the manufacturer.

5.5.10. Brackets for heating devices should be secured:

TO concrete walls dowels;

TO brick walls with dowels or sealing the brackets with cement mortar of grade no lower than 100 to a depth of at least 100 mm (excluding the thickness of the plaster layer).

The use of wooden plugs for embedding brackets is not allowed.

5.5.11. Axes of connected risers wall panels must match the built-in heating elements during installation.

The connection of risers should be made by overlap welding (with one end of the pipe spreading out or connecting with a threadless coupling).

The connection of pipelines to air heaters (heaters, heating units) must be made on flanges, threads, welding or bellows connections (see GOST R 50619) from flexible stainless pipes.

Suction and exhaust ports heating units They must be closed before they are put into operation.

5.5.12. Valves and check valves must be installed in such a way that the coolant flows under the valve.

Check valves must be installed horizontally or strictly vertically, depending on their design.

The direction of the arrow on the body must coincide with the direction of movement of the medium.

5.5.13. The spindles of double adjustment valves and regulating straight-through valves should be installed:

Vertically when heating devices without niches are located;

At an angle of 45° upward when heating devices are located in niches.

The spindles of three-way valves must be positioned horizontally.

5.5.14. Thermometers on pipelines must be installed in sleeves, and the protruding part of the thermometer must be protected by a frame.

On pipelines with a nominal bore up to 57 mm inclusive, an expander should be provided at the location where thermometers are installed.

Temperature sensors are installed in accordance with the requirements and technical documentation of the manufacturer.

6. Testing of internal sanitary systems

6.1. General provisions for testing cold and hot water supply, heating and heat supply systems

6.1.1. Upon completion of installation work, the following must be carried out:

Testing of heating systems, heat supply, internal cold and hot water supply using the hydrostatic or manometric method in accordance with GOST 25136 with drawing up a report in the form in accordance with Appendix B, as well as flushing of systems;

Individual tests of installed equipment (see 6.2) with drawing up a report in the form given in Appendix D;

Thermal test heating systems for uniform heating of heating devices.

Testing of systems using plastic pipelines should be carried out taking into account SP 40-102-2000.

Tests must be carried out before finishing work begins.

6.1.2. During individual testing of equipment, the following work must be performed:

Compliance check installed equipment and completed works of project documentation;

Equipment testing for Idling and under load for 4 hours of continuous operation. At the same time, the balancing of wheels and rotors in pump and smoke exhauster assemblies, the quality of the stuffing box packing, the serviceability of starting devices, the degree of heating of the electric motor, and compliance with the requirements for assembly and installation of equipment specified in the technical documentation of the manufacturers are checked.

6.1.3. Tests by the hydrostatic method of heating systems, heat supply and water heaters must be carried out at a positive air temperature in the premises of the building in accordance with GOST 30494.

Hydrostatic testing of cold and hot water supply systems must be carried out at an ambient temperature of not lower than 278 K (5 °C), and the water temperature must also be not lower than 278 K (5 °C).

6.2. Internal cold and hot water supply systems

6.2.1. Internal cold and hot water supply systems must be tested by hydrostatic or manometric method in compliance with the requirements of GOST 24054 and GOST 25136.

Hydrostatic and pressure testing of cold and hot water supply systems must be carried out before installing water fittings using measuring instruments in accordance with GOST 2405.

6.2.2. With the hydrostatic test method, systems are considered to have passed the test if within 10 minutes. being under pressure, no pressure drop of more than 0.05 MPa (0.5 kgf/cm 2) and drops in welds, pipes, threaded connections, fittings and water leakage through flushing devices were detected.

At the end of the hydrostatic test, it is necessary to release water from the internal cold and hot water supply systems.

6.2.3. Manometric tests of the internal cold and hot water supply system should be carried out in the following sequence:

Fill the system with air at an excess pressure of 0.15 MPa (1.5 kgf/cm2), if installation defects are detected by ear, the pressure should be reduced to atmospheric pressure and the defects eliminated;

Fill the system with air at a pressure of 0.1 MPa (1 kgf/cm2), maintain it under pressure for 5 minutes.

The system is considered to have passed the test if, when it is under pressure, the pressure drop does not exceed 0.01 MPa (0.1 kgf/cm2)

6.3. Heating and heat supply systems

6.3.1. Testing of water heating and heat supply systems should be carried out with the boilers and expansion vessels turned off using the hydrostatic method with a pressure equal to 1.5 operating pressure, but not less than 0.2 MPa (2 kgf/cm2) at the lowest point of the system.

The system is considered to have passed the test if within 5 minutes. when it is under pressure, the pressure drop will not exceed 0.02 MPa (0.2 kgf/cm 2) and there are no leaks in welds, pipes, threaded connections, fittings, heating devices and equipment.

The pressure value during the hydrostatic test method for heating and heat supply systems connected to heating plants must not exceed the permissible value overpressure for heating devices and heating and ventilation equipment installed in the system.

6.3.2. Manometric tests of heating and heat supply systems should be carried out in the sequence specified in 6.2.3.

6.3.3. Systems panel heating should be tested, as a rule, using the hydrostatic method.

Note- Manometric testing of panel heating systems can be carried out at negative outdoor temperatures.

6.3.3.1. Hydrostatic testing of panel heating systems must be carried out (before sealing the installation windows) with a pressure of 1 MPa (10 kgf/cm2) for 15 minutes, while the pressure drop is allowed no more than 0.01 MPa (0.1 kgf/cm2).

6.3.3.2. For panel heating systems combined with heating devices, the pressure value should not exceed the permissible excess pressure for the heating devices installed in the system.

6.3.3.3. The pressure value of panel heating systems, steam heating and heat supply systems during manometric tests should be 0.1 MPa (1 kgf/cm2).

The duration of the test is 5 minutes.

The pressure drop should be no more than 0.01 MPa (0.1 kgf/cm2).

6.3.4. Steam heating systems with a working pressure of up to 0.07 MPa (0.7 kgf/cm2) must be tested by the hydrostatic method with a pressure equal to 0.25 MPa (2.5 kgf/cm2) at the lowest point of the system.

6.3.4.1. Steam heating systems with an operating pressure of more than 0.07 MPa (0.7 kgf/cm2) must be tested by the hydrostatic method at a pressure equal to the operating pressure plus 0.1 MPa (1 kgf/cm2), but not less than 0.3 MPa ( 3 kgf/cm 2) at the top point of the system.

6.3.4.2. Tests steam systems carried out in accordance with GOST 24054 and GOST 25136.

6.3.4.3. The system is considered to have passed the pressure test if within 5 minutes. when it is under pressure, the pressure drop will not exceed 0.02 MPa (0.2 kgf/cm 2) and there are no leaks in welds, pipes, threaded connections, fittings, heating devices.

6.3.4.4. Steam heating systems after hydrostatic or pressure testing must be checked by starting steam at the operating pressure of the system; steam leakage is not allowed.

6.3.5. Thermal testing of heating systems at positive outside temperatures must be carried out at a water temperature in the supply lines of the systems of at least 333 K (60 °C). In this case, all heating devices must warm up evenly.

If there are no heat sources during the warm season, a thermal test of heating systems must be carried out as the system is connected to the heat source.

6.3.6. Thermal testing of heating systems at negative outside air temperatures must be carried out at a coolant temperature in the supply pipeline corresponding to the outside air temperature during testing according to the heating temperature schedule, but not less than 323 K (50 °C), and the circulating pressure in the system according to the design documentation .

Thermal testing of heating systems should be carried out within 7 hours, while checking the uniformity of heating of the heating devices (to the touch).

7. Starting heating systems

7.1. Acceptance into operation of heating systems, hot and cold water supply must be carried out in compliance with SNiP 3.01.04-87.

Before commissioning and handing over heating, hot and cold water supply systems to the operating organization, the work performer must check:

The state of insulation of heated buildings (sealing leaks in window and doorways, places where communications pass through the walls of the building, insulation stairwells and so on.);

Serviceability of thermal insulation of the heating unit, pipelines, fittings and equipment;

Availability and compliance with the calculation of restrictive diaphragms and balancing valves;

Availability and serviceability of instrumentation, control and safety devices;

The absence of jumpers between the supply and return pipelines of the heating unit and in the heating system or their reliable shutoff;

Compliance with the working documentation for connections of equipment of thermal units with water supply and sewerage.

7.2. Starting up a water heating system (and/or heat supply system, ventilation and air conditioning system, air-heat curtains) includes:

Emptying from tap water all systems filled during flushing or pressure testing;

Filling all systems with network water or filling previously unfilled systems with water from the heating network;

Creating circulation in the system using a pump;

Adjusting the start of the water system.

7.3. Before filling the heating system, all shut-off and control valves (with the exception of the first valves of the heating unit on the network side) and air valves in high points systems must be open, the first valves and drains must be closed.

7.4. Filling the heating system should be done by smoothly opening the first valve on the network side on the return pipeline of the heating unit. The water supply, controlled by the degree of opening of the valve, must ensure complete removal of air from the system. In this case, the pressure in the return pipeline of the heating unit from the network side should not decrease by more than a pressure of 0.03 to 0.05 MPa (0.3 to 0.5 kgf/cm2).

7.5. During filling of the heating system, continuous monitoring of the air valves is necessary. The air valves should close as air stops escaping and water appears.

7.6. After filling the heating system and closing the last air valve, you should smoothly open the valve on the supply pipe of the heating unit, which creates water circulation in the system.

7.7. If there are water flow metering devices (water meters) on the return pipelines, filling should be done through bypass lines; if there are no metering devices, filling should be done through an insert installed in their place. It is prohibited to fill the system through a water meter.

7.8. If the pressure in the return pipe of the heating unit is lower than the static pressure in the system, filling the heating system should begin through the return pipe. If there is no pressure (pressure) regulator on the return line of the heating unit, before starting to fill the heating system, install a throttle diaphragm taking into account SP 41-101-95, which will provide the necessary pressure at the calculated water flow in the system.

If there is a pressure regulator, the pipeline is closed manually.

When the first valve on the network side on the return pipeline of the heating unit is smoothly opened, the system is filled to the possible value determined by the pressure in the return pipeline. Further filling is carried out by smoothly opening the valve on the supply pipeline. Before performing this operation, in the absence of a pressure regulator, the valve on the return pipeline must be closed (not completely).

The valve on the supply pipe should be smoothly opened until the pressure in the heating system reaches the static pressure and water appears from the highest air valve.

The readings of pressure gauges and air valves must be monitored.

Before closing the last air valve, close the valve on the supply line and establish static pressure in the return line using the valve or by adjusting the pressure regulator spring. When closing the last air valve, you must carefully ensure that at the moment of closing the pressure in the return pipeline does not exceed the static pressure by more than 0.05 MPa (0.5 kgf/cm2).

7.9. After closing the air valve, the valve on the supply and return pipelines alternately open completely, and the pressure in the return pipeline must be maintained at a level exceeding the static one by 0.05 MPa (0.5 kgf/cm2), using a regulator or throttle diaphragm, taking into account SP 41-101-95. In this case, the pressure should not exceed that permissible for a given heat consumption system.

Note- When using a throttle diaphragm, it must be taken into account that it ensures the specified pressure in the system only when constant flow water for which the throttle diaphragm is designed.

7.10. After circulation is created, air is released from the air collectors at intervals of 2 to 3 hours until it is completely removed.

7.11. After turning on the heating system for full circulation, the pressure (pressure difference on the supply and return pipelines) and water flow at the heating unit must be equal to the calculated values.

If a deviation of the design pressure indicator by ±20% or more and water consumption by ±10% or more is detected, the causes of these deviations must be identified and eliminated.

7.12. Commissioning of heating, cold and hot water supply systems is documented in the acts given in Appendices D and E.

Appendix A
(informative)

DIMENSIONS OF HOLES AND GROOVES FOR LAYING PIPELINES (AIR DUCTES) IN FLOORS, WALLS AND PARTITIONS OF BUILDINGS AND STRUCTURES

Purpose of the pipeline (air duct)

Size, mm

holes

Heating

Riser of a single-pipe system

Two risers of a two-pipe system

Connections to devices and couplings

Main riser

Highway

Water supply and sewerage

Water riser:

One water riser and one sewer riser diameter, mm:

One sewer riser with diameter, mm:

Two water risers and one sewer riser with a diameter, mm:

Three water risers and one sewer riser with diameter, mm:

Water line:

Sewer line, water main

sewer

Inputs and outputs of external networks

Heat supply, not less

Water supply and sewerage, no less

Ventilation

Air ducts:

round section (D - duct diameter)

rectangular section (A and B - dimensions of the sides of the air duct)

Note- For openings in slabs, the first dimension means the length of the opening (parallel to the wall to which the pipeline or duct is attached), the second dimension means the width. For holes in walls, the first size means width, the second - height.

Appendix B
(required)

Form of inspection report for hidden work

ACT
INSPECTION OF HIDDEN WORK

(Name of works)

completed in ______________________________________________________________

(name and location of the object)

"____" ______________ 20___

Commission consisting of:

representative of the construction and installation organization __________ (last name, initials, position)

representative of the customer's technical supervision ________________ (last name, initials, position)

representative of the design organization (in cases of designer supervision of the design organization) _____________________________________________________

(surname, initials, position)

inspected the work performed by __________________________________________

(name of construction and installation organization)

and drew up this act as follows:

1. The following works are submitted for inspection: _______________________

(name of hidden work)

2. The work was carried out according to design and estimate documentation ________________________

_

(name of the design organization, drawing numbers and date of their preparation)

3. When performing work, __________________________________________ were used

(name of materials,

__________________________________________________________________________

documents confirming quality)

4. When performing work there are no (or allowed) deviations from

design and estimate documentation _____________________________________________

(if there are deviations, indicate

__________________________________________________________________________

approved by whom, drawing numbers and approval date)

5. Date: start of work ________________________________________________________________

completion of work _________________________________________________________________

Commission decision

The work was carried out in accordance with design and estimate documentation, standards, building codes and rules and meet the requirements for their acceptance.

Based on the above, subsequent

Construction (installation) work ________________________________________________

(name of works and structures)

Representative of the construction and installation organization _____________________

(signature)

Customer representative ______________________________

(signature)

Representative of the design organization ___________________________________

(signature)

Appendix B
(required)

Form of hydrostatic or manometric leak test report

ACT
HYDROSTATIC OR MANOMETRIC TIGHTNESS TEST

(system name)

mounted in __________________________________________________________

(name of object, building, workshop)

__________________________ "_____" ______________ 19__

A commission consisting of representatives;

customer ___________________________________________________________________

__________________________________________________________________________

general contractor _____________________________________________________

___________________________________________________________________________

installation (construction) organization ________________________________________

(name of organization, position, initials, surname)

___________________________________________________________________________

carried out an inspection and quality control of the installation and drew up this report on the following:

1. Installation was carried out according to the project _____________________________________________

(name of design organization and drawing numbers)

__________________________________________________________________________

2. The test was carried out ___________________________________________________

(hydrostatic or manometric method)

pressure ___________________________ MPa (_____________________ kgf/cm2)

within _________________________________ minutes

3. The pressure drop was __________ MPa (____________________ kgf/cm2)

4. Signs of rupture or violation of the strength of the connection of boilers and water heaters, drops in welds, threaded connections, heating devices, on the surface of pipes, fittings and water leakage through water fittings, flushing devices, etc. not detected (cross out what is unnecessary).

Commission decision:

Installation was carried out in accordance with the design documentation, valid technical specifications, standards, building codes and rules for the production and acceptance of work.

The system is recognized as having passed the pressure leak test.

Customer representative ___________________________________

(signature)

Representative of the General

contractor _____________________________________

(signature)

Assembly representative

(construction) organization _________________________

(signature)

Form of individual equipment testing report

ACT
INDIVIDUAL TESTING OF EQUIPMENT

___________________________________________________________________________

(name of the construction site, building, workshop)

Completed in _________________________ “____” _________________ 20___

Commission consisting of representatives:

Customer _________________________________________________________________

(name of organization, position, initials, surname)

general contractor__________________________________________________________

(name of organization, position, initials, surname)

installation organization _____________________________________________________

(name of organization, position, initials, surname)

have drawn up this act on the following:

__________________________________________________________________________

fans, pumps, couplings, self-cleaning filters with electric drive,

__________________________________________________________________________

control valves for ventilation (air conditioning) systems

__________________________________________________________________________

(system numbers are indicated)

have been run-in for _____________ in accordance with the technical specifications and passport.

1. As a result of running-in of the specified equipment, it was established that the requirements for its assembly and installation given in the documentation of the manufacturers were met and no malfunctions were found in its operation.

Customer representative _____________________________________

(signature)

Representative of the General

contractor ________________________________________________

(signature)

Assembly representative

organizations _____________________________________________

(signature)

Form of acceptance certificate for internal cold and hot water supply systems

We checked and accepted the internal cold and hot water supply systems of the building for the effect of action at the address _____________________________

and installed:

1. Systems tested hydraulic pressure at _____ atm.

(act no., date)

comply with the project and SNiP 3.05.01-85

2. When testing the effect of internal water supply systems, it was found that cold and hot water flowed normally to all water points.

3. The agreement for the installation of apartment water meters for cold and hot water was concluded with a specialized organization _______________________________________

"____" _____________ 200_ No. _________

Based on the inspection and testing performed, the internal cold and hot water supply system presented for delivery is considered accepted for operation.

Form of acceptance certificate for internal heating systems

We checked and accepted the heating system for its effect at the address:

___________________________________________________________________________

(administrative district, block, street, house and building number, purpose of the object)

and installed:

1. The heating system was installed in accordance with the design and technical documentation and tested in accordance with the project and the requirements of SNiP 3.05.01-85 with hydraulic pressure at... atm. (see act dated “___” __________).

2. The expansion vessel is installed in the central heating substation (ITP) in building No. ___ in accordance with the design, insulated and provided with automatic make-up.

3. Automated node control unit (AUU) (when connecting the building through a central heating substation) is installed and operates in accordance with the design and regulatory and technical documentation and provides coolant parameters corresponding to the temperature schedule and design pressures.

4. Thermostatic automatic valves Heating devices are installed in accordance with the design and have temporary protective caps or thermoelements (heads). In case of failure to install thermoelements (heads) for the period of acceptance of the heating system, an agreement with a specialized organization No. ___ dated __________ on acceptance for storage and subsequent installation of thermoelements is presented.

(heads)

5. B two-pipe system heating on thermostatic valves, the valves were installed to positions corresponding to the design values ​​for each room.

6. If there are balance valves on sectional units and risers of the heating system, the valves have been installed to positions corresponding to the design values ​​for each riser.

7. Checking the effect of the entire heating system as a whole (with installed thermostatic elements) showed that at outside air temperature Tn = _______ degrees. C, supply water temperature at control units Tk = _____ degrees. C, return water temperature To = _____ degrees. C, circulation pressure _____ m, while all heating system devices had uniform heating. Temperature in interior spaces amounted to _______ degrees. WITH.

Based on the inspection and testing performed, the heating system presented for delivery is considered accepted for operation.

Bibliography

Town Planning Code of the Russian Federation

Federal Law of December 30, 2009 No. 384-FZ “Technical Regulations on the Safety of Buildings and Structures”

Federal Law No. 261-FZ “On energy saving and increasing energy efficiency and on introducing amendments to certain legislative acts of the Russian Federation”

Order of the Ministry of Regional Development of the Russian Federation dated December 30, 2009 No. 624 “On approval of the List of types of work for engineering surveys, for the preparation of design documentation, for construction, reconstruction, major repairs of capital construction projects that affect the safety of capital construction projects”

Device rules and safe operation steam and hot water pipelines. Approved by resolution of Gosgortekhnadzor

TU 6-05-1388-86

FUM thread sealing tape

Enlarged assembly units made of steel pipes for internal water supply, hot water supply and heating systems

SP 40-102-2000

Design and installation of pipelines for water supply and sewerage systems using polymer materials

Introduction
1 area of ​​use
2 Normative references
3 Terms and definitions, designations and abbreviations
4 General provisions
5 Pressure pipe products
5.1 Requirements for pressure pipe products
5.2 Pressure pipes
5.2.1 Pressure steel pipes
5.2.1.1 Connecting parts for steel pipes
5.2.1.2 Connections for steel pipes
5.2.2 Pressure copper pipes
5.2.2.1 Connections for copper pipes
5.2.2.2 Connections for copper pipes
5.2.3 Pressure metal-polymer pipes
5.2.3.1 Connecting parts for metal-polymer pipes
5.2.3.2 Connections for metal-polymer pipes
5.2.4 Pressure pipes made of polypropylene
5.2.4.1 Connections for polypropylene pipes
5.2.4.2 Connections for polypropylene pipes
5.2.5 XLPE pressure pipes
5.2.5.1 Connecting parts for cross-linked polyethylene pipes
5.2.5.2 Connections for XLPE pipes
5.2.6 Chlorinated polyvinyl chloride pressure pipes
5.2.6.1 Connections for chlorinated polyvinyl chloride pipes
5.2.6.2 Connections for chlorinated polyvinyl chloride pipes
5.2.7 Polybutene pressure pipes
5.2.7.1 Connections for polybutene pipes
5.2.7.2 Connections for polybutene pipes
5.2.8 Acrylonitrile butadiene styrene pressure pipes
5.2.8.1 Connecting parts for acrylonitrile butadiene styrene pipes
5.2.8.2 Connections for acrylonitrile butadiene styrene pipes
5.3 Technological features of connecting pressure polymer pipes
5.3.1 Types of connections for pressure polymer pipes
5.3.2 Welding of polyolefin pressure pipe products
5.3.3 Connections of pressure pipe products made of unplasticized polyvinyl chloride, chlorinated polyvinyl chloride and acrylonitrile butadiene styrene
5.3.4 Welding pressure pipe products made of polypropylene
5.4 Fastening of pressure pipelines
6 Sewer pipe products
6.1 Requirements for sewer pipe products
6.2 Sewer pipes
6.2.1 Gray cast iron sewer pipes
6.2.1.1 Connecting parts for sewer pipes made of gray cast iron
6.2.1.2 Connections for sewer pipes made of gray cast iron
6.2.2 Ductile iron sewer pipes
6.2.2.1 Connecting parts for sewerage pipes made of ductile cast iron
6.2.2.2 Connections for ductile iron sewer pipes
6.2.3 Unplasticized polyvinyl chloride sewer pipes
6.2.3.1 Connecting parts for sewer pipes made of unplasticized polyvinyl chloride
6.2.3.2 Connections for sewer pipes made of unplasticized polyvinyl chloride
6.2.4 Thick-walled sewer pipes made of polyvinyl chloride
6.2.4.1 Connecting parts for thick-walled PVC sewer pipes
6.2.4.2 Connections for thick-walled PVC sewer pipes
6.2.5 Polyethylene sewer pipes
6.2.5.1 Connecting parts for sewer pipes made of polyethylene
6.2.5.2 Connections for polyethylene sewer pipes
6.2.6 Filled polyethylene sewer pipes
6.2.6.1 Connecting parts for sewer pipes made of filled polyethylene
6.2.6.2 Connections for sewer pipes made of filled polyethylene
6.2.7 Polypropylene sewer pipes
6.2.7.1 Connecting parts for sewer pipes made of polypropylene
6.2.7.2 Connections for socketed sewer pipes made of polypropylene
6.2.8 Filled polypropylene sewer pipes
6.2.8.1 Connecting parts for sewer pipes made of filled polypropylene
6.2.8.2 Connections for sewer pipes made of filled polypropylene
6.2.9 Connections for assembling different sewer pipes
6.3 Fasteners for gravity pipelines
7 Pipe procurement work
7.1 Bending pipes for pressure and sewer pipelines
7.2 Production of pipe blanks from pressure pipes for water pipelines
7.3 Production of liners from pressure polyethylene pipes for water supply systems
7.4 Production of pipe blanks for internal fire water supply systems
7.5 Manufacturing of water seals for internal drains
7.6 Manufacturing of units from polymer sewer pipes
7.7 Equipping package shafts with pressure water supply and sewer pipe blanks
7.8 Equipping plumbing cabins with pressure water supply and sewer pipe blanks
7.9 Manufacturing riser bays for internal drains
8 Installation of internal water pipes
8.1 Typical structures of technological processes for installing internal water supply systems
8.2 Technical documentation for installation and assembly work
8.3 Organization of work on installation of internal water supply systems
8.4 Preparatory work
8.5 Auxiliary work
8.6 Assembly of internal water pipes
9 Installation of sewer pipelines
9.1 Typical structures of technological processes for installing internal sewerage
9.2 Requirements for the internal sewerage design
9.3 Requirements for the installation project of internal sewerage
9.4 Assembling the internal sewer system
9.5 Quality control of sewer pipeline assembly
10 Installation of internal drains
10.1 Installation of internal drainage systems
10.2 Typical structures of technological processes for installing internal drains
10.3 Carrying out installation work on the assembly of internal drains
10.4 Quality control of internal drains assembly
11 Testing of internal piping systems
11.1 Testing cold and hot water pipes
11.2 Testing of fire water pipes
11.3 Testing of sewer pipelines
11.4 Testing internal drains
12 Handover and acceptance of internal pipelines
12.1 General provisions
12.2 Handover and acceptance of internal water pipelines
12.3 Delivery and acceptance of internal sewerage
12.4 Handover and acceptance of internal drains
13 Safety precautions, fire safety and environmental safety when installing internal pipeline systems
Appendix A (for reference). Symbols for sewer pipe products
Appendix B (recommended). Form of inspection report for hidden work on internal water supply and sanitation systems
Appendix B (recommended). Form of report based on test results of cold/hot water supply
Appendix D (recommended). Form of report based on test results of the internal sewerage system
Appendix E (recommended). Form of report based on the test results of the internal drainage system
Appendix E (recommended). Sample certificate of testing the internal fire-fighting water supply system for operability
Appendix G (recommended). Sample test report for internal fire water supply for water loss
Appendix I (recommended). Sample test report for fire hydrants for serviceability
Appendix K (recommended). Sample acceptance certificate for internal fire-fighting, utility and hot water pipelines
Appendix L (recommended). Sample certificate of acceptance of internal sewerage
Appendix M (recommended). Sample acceptance certificate for internal drains
Bibliography