An estimate is one of the most important documents from which the repair, construction or reconstruction of any facility begins. Drawing up an estimate for apartment renovation is a mandatory procedure that is primarily necessary for the Customer. This fundamental document must be prepared as an annex to the contract.

ORDER AN APARTMENT RENOVATION

Calculation of estimates for apartment renovations is carried out by a specialist - estimator. To begin with, our specialist goes to the repair site, inspects the premises, takes measurements of the premises, gets acquainted with the condition of the floors, ceilings, walls, windows and doors, finds out the individual wishes of the Customer and receives technical specifications.

Based on all the information received and measurements of the premises, project documentation and an estimate is drawn up for major renovation apartments. You can, perhaps, do without an estimate only if you are carrying out small redecorating or partial renovation of the interior. But still, an estimate is always needed; a description of the types of work included in the estimate undoubtedly provides a number of advantages when working on a construction site during repairs. Thanks to the preliminary estimate, the Customer receives detailed information on the list of types of work and materials required for repairs, and also sees an accurate calculation of the cost of these finishing works and materials.

Typical commercial estimate It looks like an Excel table, which must indicate the types of work, units of measurement and cost. Our company uses the services of experienced estimators; we also constantly monitor prices for building materials, which allows us to significantly save money.

You, as a customer, have the opportunity to control the progress of work and expense items. When choosing contractor to carry out the work, it is the analysis of the estimate that gives a complete picture of the cost of the work and allows us to evaluate the professionalism of the contractor.

We can immediately tell you that the prices for comprehensive renovation significantly lower than for certain types of work. Each order is individual! The cost of services depends on the types of work and their volume. Moreover, the larger the volume, the lower the price for repair and finishing work.

Sample estimate for finishing work

No./pos.

Name of works

unit.

Quantity

Price, rub

Amount, rub

Dismantling work, garbage removal

Cleaning

Cleaning walls down to concrete (from wallpaper, putty)

Cleaning the ceiling down to the concrete (high-pressure paint, putty

Cleaning the floor down to concrete (from the old coating)

Other dismantling

Dismantling the baseboard

Taking out the trash

Removal of construction waste

Electrical work

Wiring of electrical, telephone and television networks in walls and ceilings

Installation of sockets, switches, spotlights, automatic machines

Plastering walls and leveling the floor (screed)

Primer for concrete walls and ceilings

Leveling ceilings (improved plaster)

Wall leveling (improved plaster)

Painting works

Wall putty

Ceiling putty

Pasting walls vinyl wallpaper

Ceiling painting water-based paint in 3 layers

Cleaning and painting pipes with heat-resistant paint

Carpentry work

Laying the ceiling cornice, filling and painting (foam or polyurethane, width up to 3 cm)

Tile work

Masonry ceramic tiles on the floor

Cleaning

Repeated cleaning throughout the renovation and at the end of the renovation

Total for finishing work:

CUSTOMER

CONTRACTOR

__________

__________

Sample estimate for rough material

No./pos.

Name

unit.

Price according to estimate, rub

Estimated amount, rub

Materials according to the main estimate

Plaster mixture "Rotband"

Betonokontakt mixture, 5kg

Insulating tape

Mounting boxes

Junction boxes

Alabaster G-5 ( gray) 20kg each

Copper wire in double insulation PUNP 3x1.5

Copper wire in double insulation PUNP 3x2.5

Putty "Vitonit-LR" (Fin.)

Ready-made finishing putty SHEETROCK 5.6kg (3.5l) ready putty

bucket 3.5l

Primer deep penetration, canister 10l

Latex-based water-based paint Fincolor Euro-7, white matte 9l

Tile adhesive Fliesenkleber KNAUF, 25kg

Polyethylene rolls 3 m wide

Dowels, screws, self-tapping screws, nails, bolts and other fasteners

Consumables and auxiliary materials, one-time tool

Total for construction and finishing materials

Transport costs, loading, overhead, contingencies, tool depreciation, budgeting, etc. from the cost of materials

Total with transportation costs and other expenses

Dismantling, construction and finishing works, waste removal

TOTAL according to estimated costs

59749

CUSTOMER

CONTRACTOR

__________

__________


For an approximate estimate of the cost of renovation of premises, use our online calculator. On our online repair cost calculator, you can calculate approximate cost repair work with rough materials. You just need to choose the type of repair (cosmetic repairs, major repairs, European-quality renovation), select the name of the room in which you are going to make repairs, then enter the area of ​​​​the room in square meters by floor, and the rest Online calculator it will calculate everything itself and display it in the column Total approximate estimated cost your renovation of premises.

Premises renovation cost calculator - online

If you do not want to manually calculate the floor area or you did not understand something when describing the calculations, then you can use our calculator and calculate floor or ceiling area automatically.

For calculation it is necessary measure in meters length, width of the room and enter the data in order by filling out the form and you will automatically receive a calculation floor or ceiling area in square meters.

Calculator for calculating floor and ceiling area

N We won’t bog you down with tedious mathematical calculations. You just need to measure the basic parameters, and the wallpaper calculator itself will roughly calculate required quantity wallpaper for your room. Those who want more accurate calculations and measurements can read the article above How to calculate how much wallpaper you need.

When planning the renovation of his apartment, the owner sometimes, in last resort thinking about renovating the balcony. This is understandable; there is often not enough money for everything at once. But is it worth putting off finishing this room for later? After all, a balcony can be turned into a full-fledged addition to our square meters.

Today it has become popular to expand the living space of an apartment by adding a balcony or loggia. But not everyone knows what renovation work for this you need to do. For the average person, work on insulating a balcony comes down to banal glazing and filling cracks polyurethane foam and installation of decorative cladding.

In reality, everything looks much more complicated. One of the main tasks is proper insulation of the balcony. Without this, expand the living space by getting a full-fledged recreation area, a small dining room or sports section, impossible.

Today the market offers a large number of insulation materials of various qualities. Each of them has its own advantages and disadvantages. These include:

  • polystyrene foam is a foamed material with a cellular structure. Very light - easy to install. Does not withstand mechanical stress, durable decoration is required;
  • extruded polystyrene foam - thermal insulation with completely closed cells. Required additional protection- direct sunlight destroys upper layer;
  • foaming polyurethane foam (PPU) - a rigid material, applied to the surface in a continuous layer up to 60 mm thick. A big plus is the absence of cold bridges. Minus - special equipment is required for spraying. It is impossible to carry out the work independently.

An example of an estimate for insulating a balcony

This is just an example of a balcony in Vladimir. For a full calculation taking into account your wishes and the scope of dismantling work, a surveyor’s visit is required. We work on weekends by prior arrangement.

In Soviet times, almost no one paid attention to the balcony. In other words, he is there and okay. For many, it then served as a smoking area or an area where they could place items that were not susceptible to frost and precipitation.

But time passed, and the 90s arrived. And then that's it more people started paying attention to these extra square meters . Someone began to consider the balcony as an additional cellar, since they had to survive only at the expense of their harvest. Someone wanted to make an additional warm room in the apartment from the balcony and use it, for example, for an office. And someone decided to combine a summer room with an adjacent room in order to increase the size of the latter.

All the desires described above are still present in people today. And their implementation, as then, is impossible without transforming the balcony into a loggia. And this already requires some financial costs. The only question is: “Which ones?”

In order to be able to get an idea of ​​how much money will be needed to repair the loggia, below is an example of an estimate for this event.

Loggia parameters taken into account in the estimate:

  • Area - 5.1 sq.m.
  • Ceiling height - 2.8 m.
  • Glazing of the loggia - 1.7x4.2 m or 7.14 sq.m.
  • Glazing on the side of the room - 4.05 sq.m.

Plan

An example of an estimate for the repair of a loggia

Note: The estimate shows average prices for Russia for 2015.

Sample ready estimate for repair and finishing work in an apartment with a total area of ​​64 m2 in a new building at the address: residential complex "Finsky-Potapovo microdistrict 3A".

Estimate No. 4 for repair and finishing work

Estimate for the purchase of rough materials

Name of works Unit change Qty

Price

in rub.

Price

in rub.

Dismantling works
1 Joining ceiling seams(Rustov) p.m. 8 150 1200
2 Dismantling sockets, switches, lamps PC. 12 75 900
3 Dismantling the electrical panel assembly PC. 1 650 650
Total: 2 750
Construction works
1 Laying partitions from tongue-and-groove blocks or foam concrete up to 100 mm thick sq.m 5,8 420 2436
2 Device metal jumper p.m. 2 280 560
3 Construction of a bathtub screen made of blocks PC. 1 1100 1100
4 Vapor thermal insulation device ("penofol", "penoplex") balcony - floor, ceiling, walls sq.m 27 360 9720
5 Coating thermal insulation device "Akterm" sq.m 0 180 0
6 Waterproofing of joints adjacent to the street sq.m 6 185 1110
Total: 14 926
Painting and plastering works
1 Plastering walls (along beacons) up to 20 mm sq.m 25 385 9625
2 Leveling walls (usually) up to 10 mm - rooms, kitchen, corridor, storage room sq.m 154,5 200 30900
3 Leveling ceilings (usually) up to 10 mm kitchen, corridor, pantry, balcony sq.m 28 250 7000
4 Sealing ceiling seams (rusts) p.m. 8 150 1200
5 Surface primer (2 layers) ceiling, walls sq.m 0 60 0
6 Final sanding of surfaces - ceiling, walls sq.m 0 45 0
7 Puttying ceilings for painting (set of works) kitchen, corridor, pantry, balcony sq.m 28 350 9800
8 Painting ceilings with high-quality paint in 2 times sq.m 28 180 5040
9 Puttying walls for painting (set of works) sq.m 154,5 280 44805
10 Painting walls with high-quality paint in 2 times sq.m 154,5 140 21630
11 Plastering window slopes up to 300 mm p.m. 15 260 3900
12 Puttying slopes for painting (set of works) p.m. 15 280 4200
13 Painting slopes with high-quality paint in 2 times p.m. 15 180 2700
14 Installation of arched painting corners with sealing of seams and joints p.m. 22 65 1430
15 Painting of pipes with a diameter of up to 50 mm p.m. 26 120 3120
Total: 145 350
Carpentry work
1 Installation door block(ready set) PC. 5 3000 15000
2 Device slatted ceilings(up to 10 sq.m) sq.m 4,4 880 3872
3 Installation plastic window sills up to 300 mm p.m. 4,5 750 3375
Total: 22 247
Tile work
1 Wall tiling (size 250-250 mm) bath, toilet sq.m 25 850 21250
2 Hatch installation PC. 1 418 418
3 Construction of a tile hatch (with installation of a mechanism) PC 1 1100 1100
4 Laying tiles on the floor (size 300-300 mm) bath, toilet, balcony sq.m 10 700 7000
5 Drilling holes in tiles PC. 12 160 1920
6 Grouting ceramic tiles (monocolor) sq.m 35 100 3500
7 Tile threshold cladding p.m. 1 1000 1000
Total: 36 188
Floor installation
1 Waterproofing of floors in bathrooms sq.m 4,4 185 814
2 Leveling screed device up to 3 mm sq.m 54,4 150 8160
3 Laying laminate (with backing) sq.m 54,4 280 15232
4 Threshold installation p.m. 3 150 450
5 Installation of skirting boards p.m. 65 130 8450
Total: 33 106
Ventilation work
1 Insert into the ventilation duct PC. 1 319 319
2 Installation ventilation duct(up to 2 m) PC 2 1650 3300
3 Fan installation (with connection) PC. 2 308 616
Total: 4 235
Heating
1 Remaking the heating radiator supply unit PC. 3 4500 13500
2 Installing a heating radiator PC. 3 1500 4500
3 Removing/installing the radiator for finishing work (without dismantling the bracket to the finished location) PC. 3 500 1500
Total: 19 500
Plumbing work
1 Temporary water supply device set 1 1650 1650
2 Installation of a plumbing fine p.m. 6 600 3600
3 Sealing a plumbing fine p.m. 6 120 720
4 Installation of a fine filter with a pressure regulator PC. 2 1400 2800
5 Collector installation (work package) PC. 2 2000 4000
6 Laying of HGV pipes (m/layer, p/propylene, p/ethylene) p.m. 26 270 7020
7 Pad sewer pipes(PVC) p.m. 5 330 1650
8 Thermal insulation of pipes p.m. 26 50 1300
9 Installation storage water heater(boiler) PC. 1 3300 3300
10 Installation of the Compact toilet PC. 1 2805 2805
11 Installation of "moidodyr" PC. 1 3000 3000
12 Mixer installation PC. 1 850 850
13 Installation hygienic shower PC. 1 850 850
14 Installation of a heated towel rail PC. 1 3300 3300
15 Bath installation PC. 1 3700 3700
16 Installing a Bathtub Faucet on a Rod PC. 1 1250 1250
Total: 41 795
Electric installation work
1 Installation of fines up to 30x30 mm p.m. 16 275 4400
2 Sealing the fine p.m. 16 35 560
3 Cabling p.m. 255 50 12750
4 Installation of a socket box (with a socket device) PC. 33 300 9900
5 Installation of overhead electrical distribution board PC. 2 650 1300
6 Installation of circuit breakers, differential circuit breakers, RCDs PC. 12 250 3000
7 Installation of socket, switch PC. 30 130 3900
8 Installation of TV, Telephone, Internet sockets PC. 3 180 540
9 Installation of TV, Telephone, Internet splitter PC. 1 280 280
10 Installation of a built-in (spot) lamp PC. 6 200 1200
11 Electrical device heated floors sq.m 2 750 1500
12 Installation of underfloor heating relay PC. 1 350 350
13 Marking electrical installation locations (without design) PC. 33 35 1155
Total: 40 835
Total for work: 360 932
Total according to estimate No. 4: 360 932

Table No. 1 of consumption rough material.

Table No. 1 according to the consumption of construction and finishing rough materials in an apartment with a total area of ​​64 m2, a new building at the address: residential complex "Finsky-Potapovo microdistrict 3A".

Examples of a table for recording the consumption of rough material

Name

material

pcs/m2

bags

price

general

price

1 “Rodband” mixture with a layer thickness of no more than 2 cm 87 370 32190
2 Sand concrete M300 with a screed layer thickness of no more than 5 cm 145 160 23200
3 Lighthouse plaster 0.6 45 40 1800
4 Lighthouse plaster 1.0 12 45 540
5 Betokontakt "EURO" 3 1350 4050
6 Primer "Prospectors" 5 450 2250
7 Foam block No. 5 in pieces 6 45 270
8 Foam block No. 7 in pieces 84 55 4620
9 Moisture-resistant plasterboard 12 2 370 740
10 Gypsum putty "Fugenfühler" 1 750 750
11 Assembly adhesive for Perlfix blocks 3 320 960
12 Tile adhesive "Flizen" 6 350 2100
13 Self-leveling floor "Prospectors" 8 320 2560
14 Putty "Vetonit" LR+ 9 750 6750
15 Spider web "Oscar" 50m2 1 1150 1150
16 Profile 27/28 "Knauf" 6 100 600
17 Profile 60/27 "Knauf" 4 130 520
18 Finishing putty "Pro Form" 1 1350 1350
19 Pendant "Knauf" 40 20 800
20 Film -150 density 60 50 3000
21 Planed timber 50/50 3 200 600
22 Planed board 150/20 3 300 900
23 Garbage bags 120 10 1200
24 Glue for cobwebs "Oscar" 1 1350 1350
25 Coating waterproofing "Ceresit 65" 6 750 4500
26 Rule 2.5 1 500 500
27 Rule 2.0 1 400 400
28 Rule 1.5 1 300 300
29 Dowel nail 60/40 2 250 500
30 Facade mesh 160 density 1 1250 1250
31 Putty "Uniflot-Knauf" 1 1100 1100
32 Bucket 12 liters 2 120 240
33 Bucket 20 liters 2 180 360
34 Tank 60 liters 1 350 350
35 Paper masking tape 5 70 350
36 Packing tape 2 70 140
37 Self-tapping screws 0.35 universal 2 130 260
38 Self-tapping screws 0.65 for wood 1 130 130
39 Self-tapping screws 0.75 for wood 1 130 130
40 Self-tapping screws 0.25 universal 2 130 260
41 Painting corner galvanized 18 35 630
42 Alabaster in bags 1 280 280
43 Silicone in tube 1 140 140
44 Glue in a tube "FixAll" 1 420 420
45 Crosses 1.5 for tile joints 4 100 400
46 Wedges for tile joints 2 100 200
47 Cable NUM 3/1.5 "Sevkabel" 100 35 3500
48 Cable NUM 3/2.5 "Sevkabel" 150 47 7050
49 Cable NUM 3/4 "Sevkabel" 36 82 2952
50 Cable NUM 3/6 "Sevkabel" 5 95 475
51 Corrugation 16 100 3 300
52 Corrugation 20 200 4 800
53 Internet cable "FTP" 10 22 220
54 TV cable "SAT 703" 40 25 1000
55 Telephone cable "KSPV" 10 12 120
56 Crab TV 1/3 1 250 250
57 Insulating tape 1 40 40
58 Punched tape 1 180 180
59 Lamp 150v 5 40 200
60 Socket boxes for concrete 50 10 500
61 Automatic 10 amp. "ABB" 2 150 300
62 Automatic 16 amp. "ABB" 3 150 450
63 Automatic 25 amp. "ABB" 5 150 750
64 RCD "ABB" 1 1250 1250
65 DIF automatic 25 amp. 1 1350 1350
66 Armature 12 3 220 660
67
68 Lifting material "in tons" 8 1500 12000
69 Delivery of materials "gazelle" 4 1500 6000
70 Total: 147 787